ACSD Discusses Stadium Improvements

Ames Community School District

Physical Plant Equipment Levy (PPEL) Committee

August 9, 2012

Find out what's happening in Ameswith free, real-time updates from Patch.

The PPEL Committee will meet in Conference Room A of the Educational Services Center, 415 Stanton Avenue, from 7 a.m. to 8 a.m.

Agenda

Find out what's happening in Ameswith free, real-time updates from Patch.

1. Approval of June 12, 2012 Meeting Minutes

2. AHS Stadium Expansion, Hill Remediation, Concessions Stand, Restrooms,

Paving, and Electrical Transformer Relocation project update.

a. Current Budget (Summary attached)

i. Including Design Fees

ii. Including Pavement Replacement

iii. Electrical Transformer relocation

iv. Musco Light relocation

b. Comprehensive Scope of work

i. Stair removal and replacement – drainage issues

ii. Retaining walls at stadium – removal

iii. Grade adjustments

iv. Masonry construction instead of wood framed

v. Code compliance – code/needs/balance for restroom facilities

c. Value Optimization session report

d. Recommend using contingency for deficit

3. Other items

a. Committee membership

b. PPEL Budget format - Karen Shimp and Gerry Peters are working on the

format

4. Next Meeting – Tuesday September 18, 2012

AHS Stadium Expansion, Hill Remediation, Concessions, Restroom Project

Budget and cost summary

July 31, 2012

Estimated

Budget Costs

Budget 1,005,000

Budget Goal (97.5%) 980,000

Estimate 1,135,000

Design Fees 85,000

Value Session ( 40,330)

AEA/Foundation Fund - net 20,000

Paving - Separate acct 50,000

Electrical - Separate acct 50,000 50,000

CIP Contingency Acct 130,000

Total 1,230,000 1,229,670

difference 330

Contingency (net) 25,330 2.1%